    A pay application (pay app) is a contractor's monthly bill on a construction project: a summary page (in the AIA format, the G702 Application and Certificate for Payment) and a line-by-line continuation sheet (the G703) that bills progress against each line of the agreed schedule of values. It shows work completed this period and to date, materials stored on site, retainage held back, payments already received and the amount due now. Most owners and lenders also require lien waivers with each pay app.

    Key takeaways

    • The schedule of values, agreed before work starts, is the backbone of every pay app; get it right and billing disputes shrink.
    • Bill progress by line item as a percentage complete, plus materials stored, then subtract retainage and earlier payments.
    • Retainage is usually held at a contract rate and often reduced or released at milestones; state law caps it on many projects.
    • Lien waivers ride along: conditional waivers with this pay app, unconditional ones for the last payment received.
    • Most delays come from mismatches: change orders not yet in the schedule of values, missing waivers or a percentage the architect won't certify.

    What's in a pay application

    Most commercial projects in the US bill on forms modeled on the American Institute of Architects' G702 and G703, or on the owner's or lender's own version of them. The names vary; the structure doesn't.

    PartWhat it shows
    Summary page (G702-style)Original contract sum, net change orders, contract sum to date, total completed and stored to date, retainage, total earned less retainage, previous certificates for payment, current payment due and balance to finish. The contractor signs it (often notarized) and the architect certifies it
    Continuation sheet (G703-style)One row per schedule-of-values line: scheduled value, work completed from previous applications, work completed this period, materials presently stored, total completed and stored to date, percent complete, balance to finish and retainage
    AttachmentsLien waivers, change order log, stored-materials documentation and anything else the contract requires

    AIA, G702 and G703 are the American Institute of Architects' trademarks; if your contract calls for the AIA documents themselves, use licensed copies.

    Step 1: build the schedule of values

    The schedule of values (SOV) breaks the contract sum into billable line items: typically by CSI division or trade (sitework, concrete, framing, electrical, plumbing), plus general conditions, insurance and fee. The owner or architect approves it before the first pay app.

    Two habits make every later pay app easier:

    • Split large lines so each can be judged on site. "Electrical $420,000" is hard to certify at 37%; "Electrical rough-in $160,000" and "Electrical trim and fixtures $110,000" are not.
    • Keep change orders as their own lines, added to the SOV once they're approved, so the original contract and the changes stay visible.

    Step 2: the math, line by line

    Each month, for every line of the schedule of values:

    1. Work completed this period: the value of work put in place since the last pay app (scheduled value × the percentage completed this period).
    2. Materials presently stored: materials delivered but not yet installed, if the contract allows billing for them (usually with invoices, photos and proof of insurance, sometimes only for on-site storage).
    3. Total completed and stored to date = previous applications + this period + stored materials.
    4. Retainage = total completed and stored to date × the retainage rate (the contract sets it; many states cap it).

    Then, on the summary page:

    LineExample (illustrative)
    Contract sum to date (original + approved change orders)$1,200,000
    Total completed and stored to date$480,000
    Retainage (10% in this example)$48,000
    Total earned less retainage$432,000
    Less previous certificates for payment$310,500
    Current payment due$121,500
    Balance to finish, including retainage$768,000

    Numbers are an illustrative example, not a benchmark. Your contract decides the retainage rate, whether stored materials can be billed and how change orders are added.

    Step 3: lien waivers and backup

    Owners and lenders don't release money against a pay app alone. Expect to include:

    • a conditional lien waiver from you for the amount of this pay app;
    • unconditional waivers from you, and usually from each subcontractor and major supplier, for the payment received on the previous pay app;
    • the change order log and backup for stored materials;
    • for lender-funded work, the lender's own draw request and title company requirements.

    The rules for those waivers depend on the state. Texas, California, Georgia and Arizona prescribe statutory forms; see our lien waiver rules by state for the forms, notarization and timing in each.

    Step 4: certification and payment

    The architect (or owner's representative) reviews the pay app against the site, may adjust percentages, and certifies the amount due. Payment terms then run from certification under the contract and, on many projects, under the state's prompt payment law.

    Most pay apps that come back are rejected for the same few reasons:

    • percentages that don't match what's on site;
    • change orders billed before they're approved;
    • stored materials without invoices or insurance certificates;
    • a missing or wrong-form lien waiver from a subcontractor;
    • math errors carried from the continuation sheet to the summary.

    Retainage on the pay app

    Retainage is held on every pay app until the contract, or state law, allows it to be reduced or released, typically at substantial or final completion. Track it per subcontract as well: you owe your subs their retainage when the owner releases yours, and many states set deadlines for passing it down. Our guide to retainage in construction covers the rules.

    Doing it in software

    Spreadsheets work until the third change order or the tenth subcontractor. The usual pain points are rolling previous-application totals forward correctly, keeping change orders in the SOV, collecting and matching waivers to each payment, and tracking retainage owed down the chain.

    Construction accounting software and construction ERPs handle much of this; see how we approach software for construction companies. Agenbord Build for general contractors is designed around this exact workflow: pay apps from the schedule of values with change orders, retainage per contract and per subcontract, and lien waivers requested and matched to each payment. It's in early access.

    This guide is general information, not legal or accounting advice. Your contract and state law govern billing, retainage and lien waivers.

    Sources

    1. American Institute of Architects - Contract documents (G702/G703 family)

    Prices, plans and laws change. We review this guide periodically; check the linked sources for the latest figures. Nothing here is legal or financial advice.

    FAQ

    Frequently asked questions.

    What is the difference between AIA G702 and G703?

    The G702 is the summary, the Application and Certificate for Payment, with contract totals, retainage, previous payments and the amount due, signed by the contractor and certified by the architect. The G703 is the continuation sheet listing each schedule-of-values line with work completed, stored materials, percent complete and retainage.

    How often do contractors submit pay applications?

    Usually monthly, on a date set in the contract (often the 25th, with payment due a set number of days after certification). Some residential and smaller commercial contracts bill on milestones instead.

    Can you bill for materials stored off site?

    Only if the contract allows it, and owners usually require invoices, proof of insurance and sometimes a bill of sale or inspection. Materials stored on site are more commonly allowed. Check your contract's stored-materials clause before you bill them.

    What is a schedule of values?

    The breakdown of the contract sum into line items, approved before the first pay application. Every pay app bills progress against those lines, so a detailed, realistic schedule of values makes each month's billing faster to prepare and to certify.

    Do I need lien waivers with every pay application?

    Most owners, lenders and general contractors require them: a conditional waiver for the current payment and unconditional waivers for the previous one, from you and often from your subcontractors and suppliers. Some states prescribe the waiver forms; check your state's rules.